Because you are working under a firm-fixed-price contract, management wants you to submit the final invoice and close out the contract as soon as possible. Before final payment on the contract can be authorized, you must
A、Prepare a contract completion statement
B、Audit the procurement process
C、Update and archive contract records
D、Settle subcontracts