The project manager discovers an unpredictable high-impact risk has become a factor in the project. self-interest among team members is keeping the issue from being reached, The project manager must act quickly to refocus the team and get the project on tack. which of following techniques should the project manager use to resolve the issue?
A、Compromise
B、Collaborate
C、Force
D、Accommodate