If the end date of an initial plan is later than the desired date, what is the FIRST action the project manager should consider?
A、Reviewing current resource on the project
B、Determining whether more work can be done in parallel
C、Starting critical path activities at their early start dates.
D、Negotiating a change in scope for an activities with negative float