A project manager runs a mission critical project with a tight schedule and budget constraints some activities are key dependencies for the other.Which of the following components should be monitored closely to keep the agreed upon project schedule baseline?
A、Riske and their mitigation plan
B、Activities on the critical path
C、Overall change control
D、To perform a task with less experience