软题库 移动APP 扫码下载APP 随时随地移动学习 培训课程
当前位置:信管网 >> 在线考试中心 >> 信息系统项目管理师题库 >> 试题查看
试卷名称 2017年信息系统项目管理师最新英语模拟题(3)
考试中心《2017年信息系统项目管理师最新英语模拟题(3)》在线考试
试卷年份2017年下半年
试题题型【单选题】
试题内容

A project to build a 1.2 kilometer runway is budgeted at US$1 million, and is estimated to a 100 meters of runway every month. The project manager is asked by senior management to report the status to the sponsor monthly using earned value management (EVM).After six months, 600 meters of the runway is completed. And US$600,000 has been spent.Which of the following should the project manager report to the sponsor?
A、The project has a cost performance index of 0.83 and a schedule performance index of 1. The project is on time, but is likely to be over budget.
B、The project has a cost performance index of 0.6 and a schedule performance index of 1. Due to the S-Curve, The project is likely to be completed on time and on budget.
C、Work is progressing well with an earned value of US$600,000, and it is expected to be completed on time
D、Work is progressing well, however, the project will to over budget. There is insufficient information available to create an estimate using EVM.


相关试题

推荐文章
合作网站内容