A project team works, overtime to compensate for resource constraints. The project manager notices a conflict between two team members is causing a split in the project team’s dynamics .What should the project manager do first to resolve the conflict and restore the project team’s focus?
A、Issue a verbal warring to the two team members causing the conflict.
B、Reallocate the resources to avoid future conflicts.
C、Meet with the team to identify key issues and allow open discussion to resolve.
D、Escalate the team conflict to the project sponsor.