试卷名称 2017年信息系统项目管理师最新英语模拟题(2)
考试中心《2017年信息系统项目管理师最新英语模拟题(2)》在线考试
试卷年份2017年下半年
试题题型【单选题】
试题内容

A particular stakeholder has a reputation for making many changes on projects. What is the BEST approach a project manager can take at the beginning of the project to manage this situation?
A、Say "No" to the stakeholder a few times to dissuade him from submitting more changes
B、Get the stakeholder involved in the project as early as possible
C、Talk to the stakeholder's boss to find ways to direct the stakeholder's activities to another project
D、Ask that the stakeholder not be included in the stakeholder listing