From a risk management prospective, a post-project review affords the opportunity for which of the following?
A、Enables the project manager to determine how must of the risk contingency fund can be distributed to the team
B、Enables corrective actions to be implemented in the preliminary project design
C、Provides insight into anticipating and minimizing the risk on future projects
D、Provides the project manager with the initial risk register for the next project assignment