Halfway through the scheduled duration of a project, the project manager finds the actual cost is US$75. 000 and the project budget is US$100. 000. Following a detailed analysis the project spending will be maintained at the current performance rate. What is the estimate at completion for the project?
A、US$125,000
B、US$135,000
C、US$166,667
D、US$175,000