A project manager is leading the implementation of a solution that involves several emerging technologies. As a result, the project manager expects that the original project planning documents may need to be updated several times throughout the project life cycle to adjust overall project direction.What should the project manager do?
A、Develop detailed project organization charts and empower subject matter experts to approve any necessary technical scope change
B、Establish a direct and dynamic communication path with senior leadership so they are engaged in every change request
C、Inform the senior leadership that the project could not be developed once the risk of failure is identified
D、Design and implement an integrate change control system to report, control, and record changes to the original project baseline