Impact scores.A project team identifies several risks and assesses probability of occurrence and potential impact on cost, schedule, and performance for each risk. This information is presented in the table shown.If meeting cost objectives is the highest priority for this project. Which is the most critical risk for the project team to address?
A、Risk A
B、Risk B
C、Risk C
D、Risk D