试卷名称 信息系统项目管理师-pmp练习题-3
考试中心《信息系统项目管理师-pmp练习题-3》在线考试
试卷年份2017年下半年
试题题型【单选题】
试题内容

The director of the business unit submits a request for a new software application. The project manager determines the need for project requirements gathering and scope developments. Which of the following activities should be performed ?
A、Create the technical specification and requirement traceability matrix.
B、Create issue log and perform risk analysis.
C、Document a product description and create a list of stakeholders.
D、Draft the current and future processes and draft the work breakdown structure.