A company has several high-priority projects. However, the company did not provide enough resources available to work on all of their project activities. What should the line managers and the project managers do ?
A、Set up a meeting and negotiate resource allocations.
B、Assign resources on a first-come, first-serve basis.
C、Allocate resources to work extra hours on multiple projects.
D、Create a matrix of virtual teams with existing resources.