The plan for a technological restructuring project is in the planning phase for months and within that time, the technology has advanced significantly. The project is scheduled to begin this month, and the scope management plan must be updated to reflect the changes in the technology. The project manager must elaborate on the potential changes to the project scope with the key stakeholders. The project manager understands that the level of uncertainly for the project will do which of the following ?
A、Stay at the level that was anticipated and planned for.
B、Initially increase and then decrease.
C、Increase.
D、Decrease.