试题内容

A new produce development project is in its closing phrase .During production, unplanned redesigning and retesting was necessary. The project manager realizes that this happened because manufacturing engineers were not included in the planning and design process.
A、Enhance individual competence
B、Document a new lesson learned
C、Perform a quality audit
D、Update risk register