试卷名称 信息系统项目管理师-pmp练习题-2
考试中心《信息系统项目管理师-pmp练习题-2》在线考试
试卷年份2017年下半年
试题题型【单选题】
试题内容

The project manager conducts an interview with a key stakeholder. This stakeholder insists that the project be completed by a certain date to allow the resulting product to be arranged manufacture in time for a critical trade exhibition. The stakeholder also insists that the product must pass existing international safety standards. The stakeholder will not release the initial fund for the project kick-off unless both conditions are included.  Where must the project manager include these conditions?
A、Project summary milestones
B、 Project contract summary
C、 Project high-level requirements
D、 Project exit criteria