软题库 移动APP 扫码下载APP 随时随地移动学习 培训课程
当前位置:信管网 >> 在线考试中心 >> 信息系统项目管理师题库 >> 试题查看
试卷名称 信息系统项目管理师-pmp练习题-1
考试中心《信息系统项目管理师-pmp练习题-1》在线考试
试卷年份2017年下半年
试题题型【单选题】
试题内容

A project manager took over a project which is in the execution phase. The customer is unable to define the project’s objectives in the required  detailed level and the project team members have started complaining that continuous changes in requirements makes estimating work effort and schedule impossible. How should the project manager proceed?
A、  Tell the customer about team members’ complaints and ask for more detailed requirements.
B、   Tell the project team members the customer is not able tell the requirements at required pace.
C、   Update the high level WBS with more detailed information when it is available.
D、   Keep the project team occupied with the current assignments.


相关试题

推荐文章
合作网站内容