Your company is receiving a shipment of goods from the sellers when you get a call from the procurement manager who tells you that the shipment does not meet the requirements of the contract. You look at the shipment yourself and determine that the shipment meets the needs of the project. What should you do next?
A、 Send the shipment back.
B、 Accept the shipment.
C、 Issue a change order to change the contract specifications.
D、 Expect to receive a claim from the seller.