On some projects,especially ones of smaller scope,activity sequencing, activity resource estimating, activity duration estimating, and () are so linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.
A、time estimating
B、cost estimating
C、project planning
D、schedule development