 (  ) is the application of planned, systematic quality activities to ensure that the project will employ all processes to meet requirements.
A.Quality assurance
B.Quality planning
C.Quality control
D.Quality cost


相关试题

69题: Both TCP and UDP belong to (  ) layer of the OSI mode。
A.session  
B.transport  
C.network   
D.data link
答案解析与讨论:www.cnitpm.com/st/2353827345.html

70题: (  ) is the budgeted amount for the work actually completed on the schedule acticity or WBS comonent during a given period。
A.Planned value
B.Actual cost
C.Earned value
D.Cost variance
答案解析与讨论:www.cnitpm.com/st/235398180.html

71题: What does a CPI of 80% mean?  (  ) . 
A. As of now we expect the total pr gject cost of 80% more  than planned
B.When the project is completed, we will have spent 80% more
C. Your project is only progressing at 80% of that planned   
D. Your project is only getting 80 cents out of every RMB invested
答案解析与讨论:www.cnitpm.com/st/2354010832.html