试卷年份2014年下半年
试题题型【单选题】
试题内容

The Perform Integrated Change  Control  process is conducted from project inception through completion and is the ultimate responsibility of the ( ).
A.Chang control board
B.Project management office
C.Project manager
D.Configuration management officer