试卷年份2009年下半年
试题题型【单选题】
试题内容

Schedule development can require the review and revision of duration estimates and resource estimates to create an approved(  )that can serve as a baseline to track progress.
A.scope statement
B.activity list
C.project charter
D.project schedule