信管网公众号
信管网订阅号
A critical path for a project is the series of activities that determine( )by which theprojectcan be completedA.the earliest timeB.the latest timeC.the total time D.the free time
信管网参考答案:A(仅供参考,欢迎评论交流) 收藏
考试信息推送
免费在线答题
优惠报班活动
直播录播辅导