软题库 培训课程
试卷年份2012年上半年
试题题型【单选题】
试题内容

Project manager believes that modifying the project scop may provide added value for the customer.The project manager should(    ).
A.change the scope baseline
B.contact the customer to determine if the change adds value
C.call a meeting of the change control board
D.change the project's objectives

查看答案

相关试题