All of followings should be done by the project manager during project control except ( ).A、Determine that a change has occurredB、Ensure that a change is agreedC、Make sure all changes are approved by managementD、Manage changes as they occur
信管网参考答案:C(仅供参考,欢迎评论交流) 收藏