(  )is a measurable, verifiable work product such as a specification, feasibility study report, detail design document, or working prototype.
A. Milestone
B. Deliverable
C. ETC
D. BAC


相关试题

57题:

(1 ) is a method of constructing a project schedule network diagram that uses boxes or rectangles,referred to as nodes,to represent activites and connects them with arrows that asow the dependencies.This method includes following types of dependcies orprecedence relationships: (2 )the initiation of the successor activity, depends upon the completion of the predecessor activity.(3)the initiation of the successor activity, depends upon the initiation of the predecessor activity.
(1)A.PDM                B.CPM               C.PERT             D.AOA
(2)A.F-S                  B.F-F                C.S-F               D.S-S
(3)A.F-S                  B.F-F                C.S-F               D.S-S

答案解析与讨论:www.cnitpm.com/st/6021.html

58题:

Estimating schedule activity costs involves developing an(1 )of the costs of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in most application areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimating process considers whether the expected savings can offset the cost of the additional design work. Cost estimates are generally expressed in units of     (2 )to facilitate comparisons both within and across projects. The(3 )describes the business need, justification, requirements, and current boundaries for the project. It provides important information about project requirements that is considered during cost estimating.
(1)A. accuracy        B. approximation       C. specification       D. summary
(2)A. activity         B. work                C. currency           D. time
(3)A. project scope statement
B. statement of work
C. project management plan
D. project policy

答案解析与讨论:www.cnitpm.com/st/6121.html

59题:

The(  )technique involves using project characteristics in a mathematical model to predict total project costs. Models can be simple or complex.
A. Cost Aggregation
B. Reserve Analysis
C. Parametric Estimating
D. Funding Limit Reconciliation

答案解析与讨论:www.cnitpm.com/st/6222.html

61题:

(  )are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion; they may also exert influence over the project and its results.
A. Controls
B. Baselines
C. Project stakeholders
D. Project managers

答案解析与讨论:www.cnitpm.com/st/6423.html

62题:

(  )is the process of obtaining the stakeholders' formal acceptance of the completed project scope. Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.
A. Project acceptance
B. Scope verification
C. Scope definition
D. WBS Creation