In (),the project scope,time,and cost are determined in the early phases of the life cycle.Any changes to the scope are carefully managed.A.predictive life cycleB.iterative life cycleC.incremental life cycleD.adaptive life cycle
信管网参考答案:A(仅供参考,欢迎评论交流) 收藏