试卷年份2011年上半年
试题题型【单选题】
试题内容

A work breakdown structure (WBS) is a tool used to define and group a project's discrete work elements in a way that helps organize and define the total work scope of the project. A WBS is most useful for( ) .
A、identifying individual tasks for a project
B、scheduling the start of tasks
C、scheduling the end of tasks
D、determining potential delays