试卷年份2009年下半年
试题题型【单选题】
试题内容

The strategies for handling risk comprise of two main types:negative risks, and positive risks.The goal of the plan is to minimize threats and maximize opportunities.When dealing with negative risks,there are three main response strategies(  ),Transfer ,Mitigate .
A.Challenge
B.Exploit
C.Avoid
D.Enhance

查看答案