试卷年份2019年下半年
试题题型【单选题】
试题内容

() is the process of identifying individual project risks as well as source of overall project risk, and documenting their character istics.
A、 identify risks
B、 monitor risks
C、 implement risks responses
D、 plan risk management


相关试题

71题: () contr ibutes to monitoring and data collection by defining secur itymonitoring and date col lect ion requi r ements.
A、 informat ion cont inuity management
B、 information cata logue management
C、 information secur ity management
D、 informat ion distr ibut ion management
答案解析与讨论:www.cnitpm.com/st/4138811777.html

72题: () seek to perform root cause investigation as to what is leading identified trends.
A、 incident management
B、 prob lem management
C、change management
D、know ledge management
答案解析与讨论:www.cnitpm.com/st/4138916043.html

73题: the () is a graph that shows the relat ionship between two var iables.
A、 histograms
B、 flowcharts
C、 matrix diagr ams
D、 Scatter diagr ams
答案解析与讨论:www.cnitpm.com/st/4139014581.html

75题: work per formance information is circulated through () pr ocesses.
A、 planning
B、 change
C、 impr ovement
D、 communicat ion
答案解析与讨论:www.cnitpm.com/st/4139218051.html