()is the process of implementing risk response plans,tracking identified risks,monitoring residual risk,identifying new risk,and evaluating risk process effectiveness throughout the project.
A、Identity risks
B、Control risks
C、Plan risk responses
D、Plan risk management



相关试题
71题:

Retail firms analyze consumer sales trends and user preference through internet user data,This belongs to ()application area.
A、big data
B、cloud computing
C、internet of things
D、artificial intelligence

答案解析与讨论:http://www.cnitpm.com/st/3579325577.html

72题:

In the following cloud computing technology architecture,()represented by number 3.

A、PaaS
B、SaaS
C、IaaS
D、cloud platform interface

答案解析与讨论:http://www.cnitpm.com/st/3579426725.html

73题:

The seven basic quality tools are used within in the context of the PDCA Cycle to solve quality-related problems.These tools are used in()in the following processes.
A、plan quality management
B、perform quality assurance
C、perform quality control
D、perform quality improvement

答案解析与讨论:http://www.cnitpm.com/st/357954627.html

75题:

( )is the approved version of the time-phased project budget,excluding any management reserves,which can only be changed through formal change control precedures and is used as a basis for comparison to actual results.
A、The control accounts
B、Funding requirement
C、The cost estimates
D、The cost baseline

答案解析与讨论:http://www.cnitpm.com/st/3579724033.html



合作网站内容