软题库 移动APP 扫码下载APP 随时随地移动学习 培训课程
当前位置:信管网 >> 在线考试中心 >> 信息系统项目管理师题库 >> 试题查看
试卷年份2017年下半年
试题题型【单选题】
试题内容

()is a document generated by the creating WBS process that support the WBS,which provides more detailed descriptions of the components in the WBS.
A、The project charter
B、The project scope statement
C、The WBS dictionary
D、The activity list


相关试题

71题: ():a cloud service,allied to the set of business terms under which the cloud service is offered.
A、Cloud service
B、Cloud service product
C、Product catalogue
D、Service catalogue
答案解析与讨论:www.cnitpm.com/st/357135862.html

72题: ()is a computer technology that headsets,sometimes in combination with physical spaces or multi-projected environments,to generate realisitic images,sounds and other sensations that simulate a user’s physical presence in a virtual or imaginary environment.
A、Virtual Reality
B、Cloud computing
C、Big data
D、Internet+
答案解析与讨论:www.cnitpm.com/st/357141390.html

73题: Validate Scope is the process of formalizing acceptance of completed().
A、project deliverables
B、WBS
C、activities
D、milestones
答案解析与讨论:www.cnitpm.com/st/3571515456.html

75题: In project network diagram,the number of critical path is().
A、none
B、only one
C、only two
D、one or more
答案解析与讨论:www.cnitpm.com/st/3571719104.html



推荐文章