A project manager present a project status report to the PMO team. A senior member of the team identifies that local authorities were not involved in the project. As a result, the company may have to pay a penalty. The project manager failed to do which of the following?
A、Stakeholder identification
B、Communication plan
C、Stakeholder management strategy
D、Requirements planning