软题库 移动APP 扫码下载APP 随时随地移动学习 培训课程
当前位置:信管网 >> 在线考试中心 >> 信息系统项目管理师题库 >> 试题查看
试卷名称 2017年信息系统项目管理师最新英语模拟题(6)
考试中心《2017年信息系统项目管理师最新英语模拟题(6)》在线考试
试卷年份2017年下半年
试题题型【单选题】
试题内容

A key project stakeholder requests that a team member make a small modification to a feature. The team member decides the change could be incorporated in a short timeframe. The team member implements the change without informing the project manager. During validate scope, the project manager finds out about the team member’s modification. After conducting a detailed analysis, the project manager finds that the team member’s initial analysis was incomplete and the modification needed additional effort and time.What should the project manager do next?
A、Proceed to the next stage by revoking the change incorporated by the team member and informing the stakeholder accordingly.
B、Discuss with the stakeholder the importance of the change, highlighting the further impact on the cost and schedule. If the stakeholder insists on including the change, report the change to the change control board for approval.
C、Inform the stakeholder about the further impact on cost and schedule due to the change. In the current stage of the project, the change cannot be included.
D、Escalate to the sponsor about the stakeholder directly interacting with the team member.


相关试题

推荐文章
合作网站内容