软题库 移动APP 扫码下载APP 随时随地移动学习 培训课程
当前位置:信管网 >> 在线考试中心 >> 信息系统项目管理师题库 >> 试题查看
试卷名称 2017年信息系统项目管理师最新英语模拟题(5)
考试中心《2017年信息系统项目管理师最新英语模拟题(5)》在线考试
试卷年份2017年下半年
试题题型【单选题】
试题内容

A project manager is developing a project for a client working on a time-and-material contracts. They have performed an earned value analysis and verified that the project can be completed earlier and under the original estimated budget. The development team, however, was contracted by the project manager’s company under a fixed-price contract. This means the profit for the project manager’s company will decrease and the project manager’s bonus, based on the project margin, will also be less than expected.What should the project manager do?
A、Inform clients that they now is included some requirements that they are original deleted
B、Ask the development team slowdown in order to realize the expected profit in this project
C、Tell clients this project can be finished earlier
D、Add new works to meet the original budget


相关试题

推荐文章
合作网站内容