试卷名称 2017年信息系统项目管理师最新英语模拟题(3)
考试中心《2017年信息系统项目管理师最新英语模拟题(3)》在线考试
试卷年份2017年下半年
试题题型【单选题】
试题内容

A project manager presents the project plan to key stakeholders, citers stakeholder input, and obtains approvals. Later, a stakeholder says that a detail in the communications plan reeds to be changed, The project manager discusses it with stakeholder and they agree to the suggested changes.What should the project manager do next?
A、Create subsidiary documents in the communications management plan.
B、Generate a change request and submit it to the change control board.
C、Keep the project plan as it has been approved by stakeholders.
D、Change the communications plan and request stakeholders’ approval.