A project has complex dependencies between activities. The activities are assigned to reach in different departments. There is a lack of skilled resources and the company experiences financial issues. Senior management does not address the prioritization of projects. Which of the following risk categories should the project manager consider when develop risk management plan?
A. Project management.
B. Technical
C. Organizational
D. External.