试题内容

The project has finally completed, however, the project was delayed, causing cost overruns at the end of project. What should the project manager do in this case?
A、Record the circumstances as lessons learned
B、 Concentrate on archiving the financial records for this project.
C、 Collect all the work of the project and compare the results to the project scope.
D、 Record the circumstances surrounding project completion during the scope validate process.