软题库 移动APP 扫码下载APP 随时随地移动学习 培训课程
试卷年份2012年下半年
试题题型【单选题】
试题内容

The project budget has been finalized.Additional work has been discovered that was not planned for in the budget or project scope. ( )could provide the fund to cover the  newly discovered work item.
A. Contingency reserve
B. Project profit
C. Management reserve
D. Special fund


相关试题

69题:

A test case normally consists of a unique identifier, requirement references from a design specification, events, a series of steps to follow, input, output, actual result, and ( )。
A. bug   
B. expected result     
C. test report     
D. traceability matrix

答案解析与讨论:www.cnitpm.com/st/2877991.html

70题:

The Systems Development Life Cycle (SDLC) is a process of creating or altering information systems, and the models and methodologies that people use to develop these systems. Sequential SDLC models, such as( ), focus on complete and correct planning to guide large   projects and risks to successful and predictable results.
A. Waterfall    
B. Extreme Programming     
C. Spiral    
D.  Rapid Frototyping

答案解析与讨论:www.cnitpm.com/st/2878991.html

71题:

Managing risk and documenting them is very important in project planning process. You are in the process of defining key risks, including constraints and assumptions, and planned responses and contingencies. These details will be included in the( )
A. project management plan
B. project baseline
C. risk response plan
D. risk baseline

答案解析与讨论:www.cnitpm.com/st/2879992.html

73题:

Several risk response strategies are available. ( ) the risk simply gives another party responsibility for its management,it does not eliminate risk.
A. Avoiding
B. Mitigating
C. Accepting
D. Transferring

答案解析与讨论:www.cnitpm.com/st/2881992.html



推荐文章
合作网站内容