You have just taken control of a project in the middle of execution and need to learn who has approval authority for revisions in scope. (  ) document provides this information.
A、Resource assignment matrix          
B、Change control plan
C、Project charter                           
D、Client organization chart


相关试题

71题:

The TCP protocol is a (   ) layer protocol,
A、physical
B、network
C、transport
D、application

答案解析与讨论:www.cnitpm.com/st/2031700.html

72题:

An example of scope verification is (   ).
A、review the performance of an installed software module
B、managing changes to the project schedule
C、decomposing the WBS a work package level
D、performing a benefit/cost analysis to determine if we should proceed with the project

答案解析与讨论:www.cnitpm.com/st/2032700.html

73题:

Your project is behind schedule due to conflict between team members .Haring resolved the conflict, to get the project back on schedule,you should consider (  ).
A、crashing the Schedule
B、performing resource leveling
C、conducting reverse resource allocation Scheduling
D、utilizing the critical chair resources

答案解析与讨论:www.cnitpm.com/st/2033700.html