软题库 培训课程
当前位置:信管网 >> 在线考试中心 >> 信息系统项目管理师题库 >> 试题查看
试卷年份2012年上半年
试题题型【单选题】
试题内容

Your project is behind schedule due to conflict between team members .Haring resolved the conflict, to get the project back on schedule,you should consider (  ).
A、crashing the Schedule
B、performing resource leveling
C、conducting reverse resource allocation Scheduling
D、utilizing the critical chair resources

查看答案

相关试题