试卷年份2013年下半年
试题题型【单选题】
试题内容

 In project management, a ( )is a list of a project’s milestones, activities, and deliverables, usually with intended start and finish date. Those items are often estimated in terms of resource allocation, budget and duration, linked by dependencies and scheduled events.
A. schedule                 
B. WBS                           
C. SOW                  
D. charter


相关试题

70题:

The length of the IPv6 address is ( ).
A. 64 bytes         
B. 128 bytes           
C. 64 bits                
D. 128 bits

答案解析与讨论:www.cnitpm.com/st/121474182.html

71题:

( )is not the advantage of GERT (Graphical evaluation and review techniques)as compared with PERT (project evaluation and review techniques).
A. Allowing looping                           
B. Allowing for dummy tasks
C. Allowing branching                       
D. Allowing multiple project end results

答案解析与讨论:www.cnitpm.com/st/121484182.html

72题:

( )can be considered as part of risk mitigation.
A. Risk identification                                
B. Purchasing insurance
C. Assessment of outcomes                
D. Assessment of  probabilities

答案解析与讨论:www.cnitpm.com/st/121494183.html