A project is nearing completion when sponsor A is replaced by sponsor B. What should the project manager do first?
A、Meet with sponsor B to determine if any project changes are needed.
B、Finish the project based on the sponsor A's goals.
C、Begin change control procedures.
D、Update the stakeholder register.