You prepared an integrated project plan and a project schedule. You submitted it to the steering committee and it was approved. Key stakeholders accepted the plan. It is time to distribute it. Both the project plan and schedule should be distributed to
A、All stakeholders in the performing organization
B、All project stakeholders
C、Project team members and the’ project sponsor
D、People noted in the communications management plan