Market dynamics have changed. The project sponsor wants to terminate the project because of its uncertain performance. What should the project manager and the project sponsor review?
A、A root cause analysis and an action plan for the technical issues
B、Project's technical and commercial goals, viability, and Profitability
C、A change request to modify the project requirements
D、Explanations of the process that caused the technical issues