Half -way through a project, a project manager discovered the earned value the past couple of months have been erroneous. What should be the project manager’s priority?
A、Make no changes but plan to discuss with the sponsor.
B、Discuss a future course of action with stakeholders.
C、Take ownership for the error and identify corrections promptly.
D、Change the schedule and plan to match the earned value reports.