During project executing, your project team member delivers a project deliverable to the buyer. However, the buyer refuses the deliverable, stating that it does not meet the requirement on page 300 of the technical specifications. You review the document and find that you agree. What is the BEST thing to do?
A、Explain that the contract is wrong and should be changed.
B、Issue a change order.
C、Review the requirements and meet with the responsible team member to review the WBS dictionary.
D、Call a meeting of the team to review the requirement on page 300.