Management tells a project manager to subcontract part of the project to a company that management has worked with many times. Under these circumstances, the project manager should be MOST concerned about:
A、making sure the company has the qualifications to complete the project.
B、meeting management’s expectations of time.
C、the cost of the subcontracted work.
D、the terms and conditions of the contract.