During the development of the project charter, the project manager identifies many highly probable risks and believes the project will fall. What is an appropriate next step?
A、Stop working on the project as the risk is too high
B、Stop working on the project charter and start work on the risk management plan
C、Continue working on the project charter and start work on the risk management plan
D、Continue working on the project charter then review it when it with the stakeholders