A team member monitoring the processes looks at the project’s control chart, There are six consecutive points below the mean, but within control limits.The project manager should take which of the following actions?
A、Adjust the process.
B、Create an Ishikawa diagram
C、Conduct a Design of experiments
D、No action is required